New Raised Pedestrian Crossing outside Māngere College

Work to commence on the new raised pedestrian crossing outside Māngere College on Monday 15 January 2024.

Information below from Auckland Transport:

Auckland Transport and our contractor Nayler Contractors Ltd are set to start work on constructing a raised Pedestrian crossing outside 24 Bader Drive in Mangere.

Where: Outside 24 Bader Drive, Mangere (Outside Mangere College)

When (start date): 15 January 2024 Hours of work 7am to 5pm and 7pm to 5am
Please note: The traffic management will remain in place 24hrs

For (duration): Approximately 4 - 5 weeks (weather dependent)

The work we’re doing.

We’re doing this work to maintain and improve your neighbourhood and to keep our communities safe. The drawings overleaf show where we’ll be working and the traffic management that will be in place. The overview of works consist of the following
• Installation of new pram crossings
• Construction kerb line and vehicle crossings
• Construction of speed table
• Line marking and signage.

We’ll do our best to start the work on time. Factors such as wet weather could mean a delayed start. If the delay is significant, we’ll notify you. We know our work can be a bit loud, and that noise – particularly at night – can be disrupting.

We try our best to avoid working at night but sometimes it is necessary in order to avoid wider disruption on the network or to get the job done faster. If we have to work at night, we’ll do our best to keep noise levels down.

We’ll handle traffic flow in and out of the area

We will implement a one-way traffic control on Bader Drive throughout the duration of the works. Traffic flow will be maintained on Bader Drive heading northwest towards McKenzie Rd. Traffic heading southeast on Bader Drive will be detoured through Ventura Street and Elmdon Street.

Please follow all signs, and traffic directions. On-street parking will be limited while we carry out the work. You may need to either park on your property or on a side road and walk to your property.

Contact Us

If you have any queries or concerns about this project, please contact AT through the details below:

The Project and Business Interface Team

Email: [email protected]

Phone: 09 930 5090

If you have any queries directly related to the construction, please contact

Traffica: Project Manager: Andrew Siriwardena

Email: [email protected]

Phone: 021 049 1572

Thank you for your understanding and co-operation whilst we carry out these essential works.

Ngā mihi, Infrastructure Project Delivery Integrated Networks

Joanne Latif